Water Extractor
Stemming Criteria
- Chapter 4.14 (1) of the Mine Health & Safety Act states in short that the employer must take reasonable steps to ensure that holes are stemmed with material determined for that purpose to prevent risk associated with explosives detonating outside the shot hole, blowouts, fly rocks and harmful gasses.
- Effective stemming is thus the most important criteria to achieve the best possible blast result
- To achieve this, the planned stemming area must be dry and filled with dry drill chippings or aggregate to confine the explosives within the hole.
- With this water extractor, the water within the stemming area can be removed in a very short time to be able to stem a dry hole.
- The type of material is dependent on the stemming length.
- Short stemming: – less than Burden, 10% aggregate may be needed.
- Longer stemming: + more than Burden, drill chippings may be used.
Price Excludes
- Installation by Mammoth Technician
- Spare Parts
- Duties and Taxes
- Freight and Insurance
Mammoth Water Extractor Benefits
Benefits of the Mammoth Water Extractor
- Comply with MH & S Act.
- Prevent risks associated with wet stemming and overcharging.
- Overcharged explosives can be timeously removed.
- Guaranteed best blast result.
- Enhance explosives efficiency.
- Reduce stemming time.
- Cost-saving – Consider drill chippings in dried out hole versus aggregate (wet hole)
Mammoth Water Extractor Technical Specifications
Water Extractor Pipe
Non Ferrous metal PVC Pipes are used for the manufacturing of the extractors.
Extractor Pipe Dimensions
50mm | 75mm | 75mm | 110mm | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Inside Diameter |
Outside Diameter |
Length | Inside Diameter |
Outside Diameter |
Length | Inside Diameter |
Outside Diameter |
Length | Inside Diameter |
Outside Diameter |
Length |
46mm | 55mm | 2m | 67mm | 91mm | 1,5mm | 67mm | 86mm | 1,5m | 104mm | 117mm | 1m |
Capacity litre | Rope | Capacity litre | Rope | Capacity litre | Rope | Capacity litre | Rope | ||||
3 | 2m | 5 | 3.5m | 5 | 3.5m | 8 | 4m |
Mammoth Water Extractor presents operational stemming challenges
Waterlogged Holes
Bottom priming is done which forces the water to the top of the charge and fills the stemming area.
Some challenges are;
- Stemming with drill chippings and aggregate.
- Water and explosives sludge in the stemming area prevents the stemming material to go down to the top of the explosives to consolidate and contain the energy.
- A charging stick is then used to tamp the chippings excessively to create stemming that should consolidate from the explosives charge. It;
- may damage the accessories.
- will create a sludge plug within the stem area with little or no consolidation.
- Fly rock, blow out, out of hole detonation, excessive air blast, harmful gasses and underperforming explosives are eminent.
The Solution – Water Extractor
The benefits of dewatering the stemming length in a charged hole.
- Ensuring that the stemming length is clear and dry.
- The intended stemming can confidently be applied.
- Chippings (dry drill chippings in ROT lengths) can be used effectively.
- Time-saver: stemming a dry hole is quicker than feeding chippings into the water and/or sludge mixture.
- Eradicate bad practices -tamping only the top of the hole which results in insufficient stemming creating blowouts and fly-rock.
- Any water depth can be removed. It’ll remove water in internal deck charged holes by lengthening rope.
- Removing excess emulsion from the hole ensures intended results.
- Better explosives efficiency
- Using the correct stemming material as intended in a dry hole will guarantee fly-rock & air blast control
Using the Water Extractor to remove water within the stemming area
This operation serves as a check to ensure that the correct stemming can be applied, and holes are not overcharged.
- Extracting water and excess explosives from the holes is a one-person operation
- The designated person to dewater the holes must follow the pump truck at a safe distance determined via risk assessment. i.e. Sm.
- He drops the extractor into the hole and removes water and emulsion sludge to a pre-determined depth as marked on the extractor’s rope.
- He pours the water outside the hole where it cannot return or flow into any other hole.
- If a hole is overcharged, remove the access explosives by pushing the pipe down into the explosive’s column to the required stemming depth with a stick of sufficient length.
- The excess explosives must be poured into the nearest primed hole.
- He repeats the process until he reaches the intended stemming depth in the explosive’s column.
- When the hole is cleared down to the twined depth, it must be left to gas and then stemmed normally.
Mammoth Water Extractor Risk Matrix
Frequency Likelihood
Frequency Level | Description | Frequency of Events |
---|---|---|
5 | Almost certain (occurs often) Expected to happen | Occurs on very Blast |
4 | Likely (known to occur) May easily happen | Occurs Once a Week |
3 | Possible (known to occur occasionally) May Happen | Occurs Once a Month |
2 | Unlikely (has occurred somewhere) May happen sometimes | Occurs Once a Quarter |
1 | Rare (could happen but unlikely) | Occurs Once a Year |
Severity Consequence
Severity Level | Impact | Health & Safety | Blasting Result & Outcome | Loss/Damage |
---|---|---|---|---|
5 | Catastrophic/Critical | – Multiple Injuries – Misfired blast – Work on dangerous ground |
– Frozen ground – Re blast & repair cost – Production interruption – Penalties |
>R 1.0 Mil |
4 | Severe/Major | – Single Fatality/Permanent disabilities – Uneven broken ground removal – Risky work environment |
– Poor fragmentation – High loading cost – Slow production – Secondary blasting |
R.0.8 – 1.0 Mil |
3 | Major/Moderate | – Reportable injury/noise induced hearing loss – Property damage |
– Flyrock – Property damage – Financial loss |
R 0.5- 0.8 Mil |
2 | Moderate/Minor | – Lost time injury/Health effect with reversible impairment | ||
1 | Minor/Low | – Medical treatment case/ Slight health effect with no impairment |
Stemming Wet Holes
- Ensure that the stemming material is suited to the stemming length to achieve the required result
- Water in the stemming area will affect the effectiveness of a consolidated stemming
- Bottom charge all water-filled holes. This will result in water on top of the charge
- Remove the water and explosives gunk in the stemming length with a water extractor before stemming the hole. The hole will be dry and the stemming can affectively be consolidated.
- 10% aggregate is normally used when;
– holes are situated in a pool of water
– to ensure the optimum fragmentation in very hard rock
– a short stemming is needed i.e., hard rock in collar area that may create slabbing.
– no flyrock is allowed in restricted areas
Drill chippings (not fine sand) can be used effectively in dry holes as indicated below
General Stemming Chart – Flyrock Effect
Hole Diameter | x Burden | Dry Hole Graded Aggregate | Graded Aggregate in Water | Dry Hole Drill Chippings | Drill Chippings in Water | Result ‐ Flyrock Effect |
---|---|---|---|---|---|---|
10 x Dia | 0.4 x B | Moderate | High | High | Excessive | |
15 x Dia | 0.6 x B | Little | Moderate | Moderate | High | |
20 x Dia | 0.8 x B | Little or none | Little | Little | High | |
25 x Dia | 1.0 x B | None | Little/none | Little/none | Moderate | |
30 x Dia | 1.2 x B | None | None | None | Little | |
35 x Dia | 1.5 x B | None | None | None | None |